Background: Restoring an Aging Corrugator at a Corrugated Manufacturing Facility
ACI’s client operates in the corrugated packaging industry where reliable corrugator performance is essential to producing board for specialized box manufacturing. The project involved a corrugator at the Brownstown, Michigan, facility that had been in operation for approximately 25 years and consisted of equipment from multiple original equipment manufacturers (OEMs).
Over time, the machine had deteriorated significantly. Equipment had broken parts, its programmable logic controllers (PLCs) were obsolete, and the control panels were in disarray. Restoring the corrugator required extensive electrical work and an approach that accounted for the existing equipment and multiple control platforms.
ACI was responsible for the electrical design and installation work needed to bring the machine back into operation. The goal was to restore the corrugator's expected speed and reliability while meeting the project's completion deadline.
The Challenge: Revamping an Obsolete, Multi-OEM Corrugator Without Complete Electrical Drawings
The corrugator presented significant challenges before the electrical installation could begin. Its aging equipment was in poor condition, components were broken, and obsolete PLCs complicated the existing control environment. The machine also combined equipment from multiple OEMs, creating additional complexity for the installation team.
In many cases, there were no electrical drawings available to work from. ACI's electrical installation team had to develop the design and drawings in the field while working through the machine's existing electrical and control requirements.
The project also required ACI to design the entire 480-volt electrical distribution system, the emergency stop (E-stop) system, and the machine interface controls. The work extended beyond wiring individual components and required the team to address the electrical infrastructure supporting the corrugator.
The completion date was critical. The manufacturer needed the corrugator ready to produce board in time to meet its own customers' requirements. Missing the deadline would have put those commitments at risk.
ACI needed to work through the existing machine's condition, develop the necessary design information, and complete the electrical installation in time to restore production.
ACI's Approach: Electrical Design & Installation for a 25-Year-Old Corrugator
ACI approached the project as a combined electrical engineering and installation effort. With many existing drawings unavailable, the installation team developed the necessary design and documentation in the field while working through the corrugator's electrical requirements.
The machine had multiple existing control platforms, and the project proceeded with the existing controls rather than installing new ones.
The scope included:
- Designing the electrical distribution system for the existing corrugator
- Designing the machine's E-stop system as part of the electrical revamp
- Designing the controls for interfaces between the machine's equipment and systems
- Developing electrical designs and drawings in the field where existing documentation was unavailable
- Executing the installation on aging machinery assembled from multiple OEMs and operating across multiple existing control platforms
The overall project took approximately 18 months from the design phase through final execution. Design and equipment procurement accounted for approximately six to eight months, while installation took about five months.
By combining field engineering with electrical installation, ACI worked through the corrugator's existing conditions and completed the work needed to return the machine to production.
The Results: ACI Restored Corrugator Production 30 Days Ahead of Schedule
ACI successfully brought the corrugator back into operation and beat the scheduled completion date by 30 days.
The manufacturer was able to produce corrugated board on time and at the speed and reliability it expected. Completing the project ahead of schedule allowed the manufacturer to meet its customers' requirements.
The project results included:
- ACI completed work 30 days ahead of schedule, beating the planned completion date by a full month
- The corrugator successfully returned to production after the electrical revamp
- The manufacturer was able to produce corrugated board on time to meet its customers' requirements
- The corrugator resumed operation at the speed and reliability the customer expected
- The project helped establish an ongoing customer relationship, with the customer continuing to call on ACI for electrical installation and engineering support
The customer summed up ACI's work with memorable feedback: “This project was surely ACI’s finest hour.”
Why This Corrugator Revamp Project Matters
Revamping an aging corrugator can be difficult when equipment has deteriorated, PLCs are obsolete, and electrical drawings are missing. These challenges become even more complicated when a machine combines equipment from multiple OEMs and must return to production by a specific deadline.
This project demonstrates the value of combining industrial electrical installation with field engineering. ACI designed the 480-volt electrical distribution, E-stop system, and machine interface controls while developing drawings in the field to address gaps in the existing documentation.
The project also highlights the importance of meeting production deadlines in corrugated packaging manufacturing. By completing the revamp 30 days ahead of schedule, ACI helped the manufacturer return the corrugator to operation in time to meet customer requirements.
For corrugated packaging manufacturers dealing with obsolete equipment, deteriorating electrical systems, or complex multi-OEM machinery, ACI provides electrical installation and engineering support to help restore production and keep projects on schedule.
Planning a corrugator revamp or a complex electrical installation for a paper and packaging facility? Talk to ACI about your project.