How ACI Helped an OEM Rewire Turbine Control Panels During a 60-Day Shutdown

Industry: Energy & Power Generation

Service: Industrial Electrical Installation

Electrical installation for power generation

Background: An OEM Needed Reliable Electrical Installation Support for a Power Generation Project

A global OEM that manufactures, installs, and maintains power generation equipment and controls partnered with ACI on a project involving turbine control systems used to generate electricity for the grid.

The project involved control systems for gas, coal, and hydro turbines and included the replacement and rewiring of 42 DCS control panels and 3 SES/SFC panels, with more than 10,000 I/O points involved.

The OEM needed an industrial electrical contractor that could work through difficult existing conditions, perform quality electrical installation and power distribution work, and meet a demanding shutdown schedule.

The Challenge: Rewiring Turbine Control Panels with Poor Existing Wiring During a Tight Shutdown

The condition of the existing panel wiring created significant challenges for the project. Many wires were not labeled, while others were too short. The engineered drawings also did not match the existing wiring layout.

The project had another major constraint: the shutdown window was 60 days from removal through return to service. The electrical installation needed to stay on schedule so the equipment could be tested, commissioned, and brought back into service within the planned timeframe.

Previous projects using other contractors presented issues including miswiring, logistical problems, poor response times, and missed deadlines. For this project, the OEM needed a partner that could execute the installation carefully and respond to field conditions as they were identified.

ACI's Approach: Electrical Installation & Power Distribution for Turbine Control Systems

ACI provided industrial electrical installation and power distribution for the project, including the replacement and rewiring of the DCS and SES/SFC panels.

The scope included:

  • Replacing and rewiring 42 DCS control panels
  • Replacing and rewiring 3 SES/SFC panels
  • Working with more than 10,000 I/O points
  • Installing OEM hardware specified for the project
  • Performing electrical installation and power distribution work from site drawings
  • Working through difficult existing wiring conditions
  • Identifying discrepancies between the engineered drawings and the existing wiring
  • Redlining and correcting those discrepancies before commissioning

One of the most important parts of ACI's approach was comparing the engineered drawings with the actual field conditions.

The drawings did not match the existing wiring layout in several areas. Rather than allowing those discrepancies to carry into commissioning, ACI identified the differences, redlined the drawings, and corrected the issues before commissioning took place.

That was particularly important given the condition of the existing wiring. With wires that were unlabeled or too short, the installation required careful attention to what was actually present in the panels rather than relying solely on the original documentation.

The shutdown portion of the work—from removal through return to service—was completed within the 60-day window.

The Results: ACI Completed the Turbine Control Panel Installation 10 Days Ahead of Schedule

ACI completed the installation in approximately 60 days, about 10 days ahead of schedule.

The project results included:

  • 42 DCS control panels replaced and rewired
  • 3 SES/SFC panels replaced and rewired
  • More than 10,000 I/O points involved
  • 100% of the panels tested and commissioned ahead of schedule
  • The plant returned to service ahead of the scheduled timeline

The project also contributed to a long-standing relationship between ACI and the OEM. ACI has worked with the company for more than 18 years, and the relationship has continued to grow stronger.

The customer describes ACI as its “go to contractor.”

For a project operating within a fixed shutdown window, completing the installation approximately 10 days early allowed the plant to return to service ahead of the scheduled timeline.

Why This Power Generation Project Matters

Turbine control system projects can become complicated when existing wiring does not match the engineering documentation, panel conditions are poor, and the installation has to be completed within a defined shutdown window.

This project demonstrates the importance of having an industrial electrical contractor that can work from engineering drawings while also responding to actual field conditions. ACI identified wiring and drawing discrepancies before commissioning, addressed the issues during installation, and completed the work ahead of the scheduled shutdown timeline.

For OEMs and power generation companies planning turbine control system work, panel replacement, rewiring, or related electrical installation, the project shows how careful field execution can help keep a complex installation moving.