Case Studies

How ACI Helped an OEM Retrofit Obsolete Control Panels

Written by ACI | Nov 24, 2026, 2:24:11 PM

Background: An OEM Needed to Retrofit Obsolete Westinghouse Control Panels

A global OEM that manufactures, installs, and maintains power generation equipment and controls partnered with ACI on a first-of-its-kind control panel retrofit at a power generation facility.

The plant's DCS control panels had become obsolete, but the existing Westinghouse panel frames had to remain in place. The retrofit involved installing new OEM hardware within the existing frames and working across thousands of I/O points.

The OEM needed an industrial electrical contractor with extensive control panel and control wiring experience that could execute the installation within an extremely short turnaround.

The Challenge: Completing a First-of-Its-Kind Control Panel Retrofit in 60 Hours

Time was the biggest constraint. The OEM needed the plant back online within 60 hours, and other OEMs had said the project could not be done.

The retrofit had never been attempted before. The OEM was adapting obsolete Westinghouse panels to accept its hardware while retaining the existing panel frames. That created a highly specialized installation with little room for delays or execution problems.

The schedule also carried significant consequences. The plant was under contract to provide steam to a neighboring manufacturing facility, and the OEM faced substantial penalties and fines if the plant was not back online within the 60-hour deadline.

ACI needed to do more than provide electricians for the installation. The team needed to understand the retrofit, determine how long the work would take, and prepare for the installation before the shutdown began.

ACI's Approach: Rehearsing the Retrofit Before the Plant Shutdown

ACI's experience with control panel work, control systems, and control wiring played a central role in preparing for the project. Rather than waiting until the installation window to work through the new panel configuration, ACI traveled to the OEM's headquarters and practiced the installation on actual panels.

This preparation allowed ACI to determine how long each panel would take and train the installation team before the critical turnaround. The hands-on practice gave the team a clear understanding of the retrofit and helped the OEM and ACI establish a realistic installation plan before work began at the plant.

ACI also provided round-the-clock coverage during the installation to maintain progress throughout the tight turnaround.

The scope included:

  • Retrofitting obsolete Westinghouse panel frames to accept OEM hardware
  • Installing and rewiring the plant's DCS control panels
  • Working with thousands of I/O points
  • Installing a custom swing arm panel developed by the OEM for the retrofit
  • Applying ACI's control wiring and control panel installation experience
  • Providing round-the-clock installation coverage
  • Preparing for the installation through hands-on training at the OEM's headquarters

The upfront preparation proved to be a deciding factor in the project's success. By practicing on the actual panels before the shutdown, ACI could enter the installation with a clear understanding of the work required and the time needed for each panel.

The Results: ACI Completed the Installation in 48 Hours

ACI completed the installation in 48 hours, finishing the critical electrical installation well within the 60-hour turnaround.

The plant startup was completed within the full 60-hour target, allowing the facility to return to service on schedule and meet its steam supply commitment.

The project results included:

  • Control panel installation completed in 48 hours
  • Plant startup completed within the 60-hour deadline
  • Obsolete Westinghouse panels successfully retrofitted for OEM hardware
  • Thousands of I/O points addressed as part of the DCS control panel work
  • Plant returned online as scheduled

The project also helped solidify the relationship between the customer and ACI. ACI has continued installing for the OEM for more than 20 years, and the relationship remains strong.

Their feedback on the project was clear: “The project could not have been done without partnering with ACI.”

Why This Control Panel Retrofit Project Matters

Retrofitting obsolete control panels can present a different set of challenges than a conventional panel replacement. Existing infrastructure may need to remain in place while newer hardware is adapted to work within a legacy system. When the work also has to be completed during an extremely short plant turnaround, preparation becomes just as important as field execution.

This project demonstrates how hands-on preparation can reduce uncertainty before a critical installation begins. ACI did not simply arrive at the plant and begin working through the retrofit. The team traveled to the OEM’s headquarters, practiced on actual panels, established installation timing, and prepared its electricians before the 60-hour window began—showing that ACI will go the extra mile to prepare for projects and meet customer expectations.

The project also demonstrates the value of experienced industrial electricians on complex control system installations. ACI's control panel and control wiring experience allowed the team to work alongside the OEM on a retrofit that had never been attempted before and complete the installation in 48 hours.

For OEMs and power generation companies dealing with obsolete control panels, legacy equipment, or demanding shutdown schedules, the project shows how thorough preparation and experienced electrical installation support can help make a challenging retrofit possible.

Planning an obsolete control panel retrofit or critical power generation installation? Talk to ACI about your project.